Longview Unit #1 Baghouse

Location: Maidsville, WV

Owner: Longview Power, LLC

Contractor: Aker Construction, Inc.

Date Completed: October 2010

Scope of Work

APi Construction secured a portion of this grassroots coal-fired power plant by insulating the AQCS ductwork and equipment. APi supplied and installed approximately 102,000 SF of insulation and lagging on two Wheelabrator Fabric Filters, two axial flow induced draft fans, and the associated AQCS ductwork.