Combined Cycle Projects
Fox Energy Combined Cycle Power Plant, Wisconsin

 

Fox Energy Phase A

LOCATION:
Kaukauna, WI
CONTRACTOR:
Calpine Construction Management Company
OWNER:
Fox Energy Company LLC
SCOPE OF WORK:
Installation of 29,000 SF of Insulation & Lagging for one Neuter Erikson HRSG, steam turbine, and 32,000 LF of insulation and pipe covering for the balance of plant piping.
DATE COMPLETED:
July, 2005

PSEG Bethlehem Balance of Plant Piping

LOCATION:
Albany, NY
CONTRACTOR:
PSEG - Public Service Electric & Gas
OWNER:
PSEG - Public Service Electric & Gas
SCOPE OF WORK:
Supply and installation of the insulation and jacketing for the balance of plant piping associated with three (3) unit combined cycle project.
DATE COMPLETED:
June, 2005

UW Madison Cogeneration Project

LOCATION:
Madison, WI
CONTRACTOR:
Alliant Energy/MG&E Construct
OWNER:
Madison Gas & Electric/University of Wisconsin
SCOPE OF WORK:
Supply and installation of the insulation system requirements for a 150 MW cogeneration unit comprised of 2 gas turbines, 2 heat recovery steam generators, and a steam turbine to supply 20,000 tons chilled water and 400,000 lbs. of steam for UW-Madison.
DATE COMPLETED:
May, 2005

PSEG Bethlehem HRSG's

LOCATION:
Albany, NY
CONTRACTOR:
Nooter Eriksen
OWNER:
PSEG - Public Service Electric & Gas
SCOPE OF WORK:
Supply and installation of the insulation and jacketing for the piping and equipment associated with 3 Nooter Eriksen HRSG-s.
DATE COMPLETED:
January, 2005

Lower Mount Bethel Energy

LOCATION:
Martins Creek, PA
CONTRACTOR:
Foster Wheeler Zack, Inc.
OWNER:
LMB Funding LLC
SCOPE OF WORK:
Complete installation of 15,000 SF of Insulation & Lagging and and 50,000 LF of Insulation & Jacketing for a 600 MW Combined Cycle Power Plant consisting of two (2) new NEM HRSG-s, two (2) Siemens Combustion Turbines, and one (1) Siemens Steam Turbine.
DATE COMPLETED:
May, 2004

PSEG Lawrenceburg Energy Facility

LOCATION:
Lawrenceburg, IN
CONTRACTOR:
Fluor Constructors Indiana Limited Partnership
OWNER:
PSEG America, PSEG Lawrenceburg Energy Company, LLC.
SCOPE OF WORK:
Complete installation of 48,000 SF of Insulation & Lagging and 84,000 LF of Insulation & Jacketing for a 1,200 MW Combined Cycle Power Plant consisting of four (4) Aalborg HRSG-s, four (4) GE Combustion Turbines, and two (2) GE Steam Turbines.
DATE COMPLETED:
March, 2004

Mirant Sugar Creek, LLC

LOCATION:
West Terre Haute, IN
CONTRACTOR:
Burns & McDonnell
OWNER:
Mirant, LLC
SCOPE OF WORK:
Complete supply and installation of 10,000 SF of Insulation & Lagging and 36,000 LF of Insulation & Jacketing required for a 550 MW Combined Cycle Power Plant consisting of 2 GE Combustion Turbines, 1 GE Steam Turbine, and 2 Vogt-Nem Heat Recovery Steam Generators.
DATE COMPLETED:
June, 2003

Zeeland Power Station - Phase II - Combined Cycle Project

LOCATION:
Zeeland, MI
CONTRACTOR:
Burns & McDonnell Engineering Co., Inc.
OWNER:
Mirant-Zeeland
SCOPE OF WORK:
Complete installation of 10,000 SF of Insulation & Lagging and 34,000 SF of Insulation & Jacketing for a 550 MW Combined Cycle Power Plant consisting of two (2) Vogt-Nem HRSG-s, two (2) General Electric Combustion Turbines and one General Electric Steam Turbine.
DATE COMPLETED:
January, 2003

<< Back

APi Construction Company
800.223.4922
www.apiconst.com

APi consistently provides its products and services at competitive prices by proactively investigating new methods of project management and installation. With over 75 years of experience, APi is an industry leader and one of the top 10 privately held firms in the field.