Completed steam turbine at Springerville Unit #3 in Arizona
Weston #4 Balance of Plant Piping and Equipment
- LOCATION:
- Rothschild, WI
- CONTRACTOR:
- Black & Veatch Construction
- OWNER:
- Wisconsin Public Service
- SCOPE OF WORK:
- Supply and installation of 212,000 SF of conventional insulation and 20,000 LF of insulation and pipe jacketing on a 500-MW Babcock & Wilcox (B&W) Supercritical Boiler and two (2) B&W SCRs. API also installed 230,000 SF of API Type I prefabricated panels on the plant AQCS to include two (2) B&W Spray Dry Absorbers, one (1) B&W Fabric Filter, ID Fans, and the associated ductwork. In addition, API installed the insulation on the balance of plant piping and equipment to include 86,000 LF of pipe and 52,000 SF of flatwork.
- DATE COMPLETED:
- March, 2008
Allan S. King Plant-2005 Fall Outage Transition Duct & MERP Project
- LOCATION:
- Bayport, MN
- CONTRACTOR:
- Xcel Energy
- OWNER:
- Xcel Energy Services, Inc.
- SCOPE OF WORK:
- Removal of approximately 74,000 SF of Insulation & Lagging for the rehabilitation of the existing Boiler and Turbine. In addition, supply and installation of approximately 605,000 SF & 23,000 LF of flatwork & piping Insulation associated with the addition of a Mitsubishi SCR, two (2) Alstom SDAs, two (2) Alstom Pulse Jet Fabric Filters, an Alstom 530MW Steam Turbine and a balance draft conversion of the existing Babcock & Wilcox Coal Fired Steam Generators
- DATE COMPLETED:
- September, 2007
Springerville Unit # 3
- LOCATION:
- Springerville, AZ
- CONTRACTOR:
- Bechtel Construction Company
- OWNER:
- Springerville Units Holding LLC
- SCOPE OF WORK:
- Supply and Installation of 140,000 SF of API Type I panel system, along with 264,000 SF of conventional installed Insulation & Lagging and 44,000 LF of piping associated with New Foster Wheeler Steam Generator, 450MW Mitsubishi Steam Turbine, Foster Wheeler SCR, two (2) Alstom Spray Dryer Absorbers and Alstom Fabric Filter Dust Collector
- DATE COMPLETED:
- July, 2006
Hardin Generation Station - Complete Coal Fired Boiler
- LOCATION:
- Hardin, MT
- CONTRACTOR:
- NewMech Companies, Inc.
- OWNER:
- Rocky Mountain Power, Inc.
- SCOPE OF WORK:
- Insulation & Lagging for a complete 113 MW Coal Fired Power Plant including one Babcock & Wilcox boiler, one Alstom SCR and one Hamon Baghouse, as well as all interconnecting ductwork, fans, air heaters, combustion air ductwork, piping and steam turbine. Completed scope included over 160,000 SF of conventional and panel insulation systems and over 20,000 lineal feet of piping.
- DATE COMPLETED:
- January, 2006
Stanton Energy Center Unit #2 Turnkey Project
- LOCATION:
- Orlando, Florida
- CONTRACTOR:
- Black & Veatch
- OWNER:
- Orlando Utilities Commission
- SCOPE OF WORK:
- Large turnkey Insulation & Lagging project including the supply and installation on a 425 MW Fossil Fuel Power Plant with the following equipment: B&W boiler, WAPC precipitator, ABB Environmental Systems scrubber, Noell, Inc. selective catalytic reduction (SCR) system, and Westinghouse turbine generator.
- DATE COMPLETED:
- June, 2001